Rough Outline of Schedule for House That She Built
February 2020 – Plans Finalized & Engineered, Design Plans Presented
March 2020 – Take Offs (Additional time for engineering if needed)
April 2020 – Focus on Missing Material Donations & Laborers
May 2020 – Round Table Meeting with Donors & Laborers
July 2020 – Finalize Participants, Donations & Schedule
August 2020 – Submit for Permit
September 2020 – Ground Breaking, Begin Foundation
October 2020 – Foundation & Sub Rough
November 2020 – Framing
December 2020 – Roughs
January 2021 – Insulation & Drywall
February 2021 – Trim Work & Paint, Exterior as Weather Allows
March 2021 – Flooring, Cabinets, Exterior
April 2021 – Countertops, Finishes, Site Concrete, Landscaping
May 2021 – Landscaping & Decor Finished
June 2021 – Parade of Homes